US Manufacturing Boom Has a Real Estate Problem
April 16, 2023
| Share:
April 13 (Reuters) – Volkswagen’s off-road brand Scout Motors studied 74 different parcels of land across the U.S. last summer as it hunted for a place to build a $2 billion assembly plant.
It quickly eliminated almost all of them. In one case, they learned it would take six years to build a needed rail link. Others lacked access to clean power – crucial for a project for “green” electric vehicles. Some did not offer enough nearby skilled labor.